- BUILDING PROCESS OF ECO SHELLS & MONOLITHIC DOMES -
____________________________________________________________________
Step 1. "FORMING STAKES" FOR AIRFORM Step 2. FORMING BOARDS INSIDE STAKES
____________________________________________________________________
Step 3. PLUMBING + ELECTRICAL
____________________________________________________________________
Step 4. REBAR CROSS PATTERN WITH CONCRETE POURED ON TOP + REBAR ON END.
____________________________________________________________________
- ECO SHELL -
Step 5. "AIRFORM" IS PLACED UNDERNEATH Step 6. CONCRETE IS APPLIED BY HAND OR WITH
CLAMP ANGLES. SHOTCRETE PUMP. 24 HOURS TO DRY.
____________________________________________________________________
- MONOLITHIC DOME -
Step 5. "AIRFORM" IS PLACED ON THE RING Step 6. SHOTCRETE IS APPLIED TO
BASE AND IT IS INFLATED. THE INTERIOR SURFACE OF THE DOME.
____________________________________________________________________
Step 7. INTERIOR PLASTER COATING IS APPLIED, THEN EXTERIOR IS COATED WITH ELASTOMERIC COATING
TO HELP WITH SOLAR REFLECTANCE + ANY LEAKS OR HAIRLINE CRACKS.
____________________________________________________________________
ECO SHELL MONOLITHIC DOME